How long will you wait on weather?
P50 and P90 waiting-on-weather days, before the vessel is booked.
Offshore campaigns live and die on weather windows and vessel day rates, and a weather-window study costs £20,000 to £200,000 per campaign. Coming soon, WeatherWise will run your task list and limiting conditions against every year in a 45-year hindcast to size the weather windows and waiting-on-weather days per task at P50 and P90, so the campaign duration and the vessel budget can reflect the sea the campaign will actually meet.
Expected: Starting from 3,500 credits per campaign
Want it when it launches? Email us about your project and we'll tell you the day it's live.
Your 1,000 free credits work on the live workflows now.
Today vs WeatherWise: time and money
| Compared | By hand, today | With WeatherWise |
|---|---|---|
| What it involves | An offshore weather-window study costs £20,000 to £200,000 per campaign today. The vessel is then chartered against that study, and the campaign hopes the year behaves. | What it will doRuns your offshore campaign against every year on record to show workable windows, waiting time and campaign duration by month. |
| Time and cost | £20,000–£200,000 per campaign | Expected: 3–5 days · 5 steps · ✓ ReviewedComing soon — your 1,000 free credits work on the live workflows now. |
By-hand figures are EHAB market benchmarks. Where they come from.
Coming soon
Why we're building the Weather Window Analysis
- 1
Offshore campaigns live and die on weather windows and vessel day rates.
- 2
Weather window studies cost £20k–£200k per campaign.
- 3
We will run your campaign against every year on record.
Where it will save you time
Waiting-on-weather days in 3–5 days, for a fraction of a study.
What happens next
- 1. Email sales@ehab.co — tell us about your project.
- 2. We email you the day the Weather Window Analysis goes live.
- 3. Expected to start from 3,500 credits; your 1,000 free credits work on the live workflows now.
Early projects help shape what it delivers.
Offshore weather windows: how it's done today
Offshore is the one part of construction that prices weather honestly, because a vessel day rate is a visible six-figure number. The analysis costs six figures too. It shouldn't.
Today, offshore weather risk is sized through a commissioned consultancy study, in four steps.
- Commission a persistence study from a metocean consultant.
- Get a weather window distribution for the season.
- Pick an alpha factor for the marine operation.
- Charter the vessel against the study and hope the year behaves.
What WeatherWise will do instead
We will run persistence and spells analysis across the full hindcast, simulate your campaign against every year on record, derive the alpha factor and hand back P50 and P90 waiting-on-weather days — with the vessel-cost exposure attached to each.
How is it calculated?
WeatherWise will use a 45-year wind and wave hindcast at the site or along the route. It will run persistence and spells analysis to find every window that meets each task's vessel limits for the required duration, then simulate the campaign against every year on record to build distributions of campaign duration and waiting-on-weather days, reported at P50 and P90. It will also derive the alpha factor used under DNV-ST-N001 to allow for forecast uncertainty. As a Reviewed workflow, an EHAB analyst will check the inputs and results before release. Full method: see our method page.
What you'll get
- Window distribution by month
- P50/P90 campaign duration
- WoW day allowance
- Vessel-cost exposure
Output Excel workbook
Who is this for?
Installation and marine planners
Campaign durations with the weather in them.
Estimators and commercial managers
Vessel and spread cost at a chosen confidence.
Developers and package managers
A consistent weather basis across contractor bids.
More for: Planners and schedulers · Estimators
Standards and contracts referenced
- DNV-ST-N001 (marine operations, alpha-factors)
- IMCA guidance
- BS 6349.
Every year on record simulated, not one representative season.
Be first to run the Weather Window Analysis.
Want it when it launches? Email us about your project and we'll tell you the day it's live. Your 1,000 free credits work on the live workflows now.
Questions about offshore weather windows
Can't find it? Email sales@ehab.co.
What is a weather window and how is it calculated?
What is waiting-on-weather and how is it priced?
Will I be able to change the vessel limits and re-run?
How will this compare with a consultancy weather-window study?
Pairs with the Weather Window Analysis
3.1Weather Downtime Allowance Report
⚡ InstantHow much weather should you allow in the bid?
Starting from 1,500 credits per programme
What it doesImports your programme, identifies weather-sensitive activities, applies trade-specific thresholds, runs 45 years of weather through Monte Carlo, and generates the resulting calendars for you to import into P6 or Asta, or syncs them into OPC.
You getDowntime calendars by activity type · P20/P50/P80 lost days · Month-by-month exposure · Audit trail
Connects to P6 · Asta · OPC · Safran
3.2QSRA Weather Risk Model
✓ ReviewedPut realistic weather risk into your QSRA
Starting from 2,250 credits per programme
What it doesReplaces a single generic weather assumption with linked weather risk distributions for the activities actually exposed.
You getWeather risk distributions · Correlation structure · P50/P80 dates · Tornado contribution
Connects to Safran · Acumen · PRA · OPC · N&L
3.3NEC Contract Weather Baseline
⚡ InstantSet the NEC weather baseline for the site
Starting from 350 credits per contract
What it doesCalculates the monthly 1-in-10-year weather values for the NEC Contract Data from the site's own 45-year record.
You getContract Data schedule · Monthly 1-in-10-year values · Bespoke measurement options
Output PDF report
Written by WeatherWise team, EHAB. Method reviewed September 2026. How WeatherWise calculates site weather.