How much weather should your bid allow?
The number that decides if the job is profitable. Set from 45 years at the site.
A weather downtime allowance is the number of working days a construction programme expects to lose to weather, by activity type and by month. WeatherWise sets it by importing your programme (.xer, .pp or .mpp), classifying the weather-sensitive activities, applying trade-specific thresholds, running 45 years of site weather through a Monte Carlo simulation, and generating P20, P50 and P80 downtime calendars to import into P6 or Asta or to sync into Primavera Cloud, or downtime samples for Safran Risk — with the audit trail that shows how the number was reached.
Starting from 1,500 credits per programme
Start on your 1,000 free credits; this workflow is priced from 1,500 credits.
Today vs WeatherWise: time and money
| Compared | By hand, today | With WeatherWise |
|---|---|---|
| What it involves | Setting a weather downtime allowance by hand takes 2 to 10 planner days and costs £1,000 to £8,000 today. It relies on limited weather data that is hard to find, may be out of date and has to be worked through by hand, which is slow and error-prone, and it leaves no audit trail. | Imports your programme, identifies weather-sensitive activities, applies trade-specific thresholds, runs 45 years of weather through Monte Carlo, and generates the resulting calendars for you to import into P6 or Asta, or syncs them into OPC. |
| Time and cost | 2–10 planner days · £1,000–£8,000 · limited, hard-to-use data · no audit trail | As little as 4 min · 5 steps · ⚡ Instant · up to 720× fasterStart on your 1,000 free credits; this workflow is priced from 1,500 credits. The exact price shows in the app before you confirm. |
By-hand figures are EHAB market benchmarks. Where they come from.
Already using activity codes
We use them as they are.
If your programme already carries activity codes, WeatherWise reads them straight in, maps the weather-sensitive work and runs. The times above assume this.
Starting from scratch
We'll set them up with you, once.
No activity codes yet? We help you build the structure one time. After that, you run as many programmes through the system as you like.
Video: Analyse your schedule with the Plan Impact Summary
Weather downtime allowance: how it's done today
Somewhere in the next tender, a planner will spend two days deciding how much weather to allow for. They'll work it out by hand from whatever data they can find: a regional average, a previous project, or an operations manager's recollection of a similar site. It will govern the largest single exposure on a two-year programme. It will leave no audit trail. And commercial review will strip half of it out to win the job.
Today, a planner sets the tender weather allowance by judgement, in five steps.
- Pick the weather-sensitive activities in the tender programme.
- Estimate by hand the percentage of working time each activity will lose to weather, from whatever weather data can be found.
- Add weather non-working days to a calendar, or a buffer bar, or nothing.
- Price the weather allowance into the tender.
- Defend the weather allowance in bid review with only limited data behind it.
What WeatherWise does instead
Upload the programme. We classify every weather-sensitive activity, apply trade-specific thresholds — wind speed for lifts, substrate temperature for pours, antecedent rainfall for earthworks — run 45 years of site weather through Monte Carlo, and generate the weather calendars for you to import into P6 or Asta, or sync them into OPC. You get P20, P50 and P80 lost days per activity type, month by month, with the evidence attached. When bid review challenges the allowance, you show them the distribution.
How is it calculated?
WeatherWise uses 45 years of world-leading reanalysis datasets, up to 9 km grid, for the site. It classifies the weather-sensitive activities in the imported programme and applies a trade-specific threshold to each, such as wind speed for lifts, substrate temperature for pours and antecedent rainfall for earthworks. A Monte Carlo simulation then runs the programme repeatedly against the 45 years of site weather to build a distribution of lost days for each activity type and month, from which P20, P50 and P80 are read. As an Instant workflow, results pass automated checks and can return in as little as a few minutes, with the thresholds and inputs recorded in the audit trail. Full method: see our method page.
What you get
- Downtime calendars by activity type
- P20/P50/P80 lost days
- Month-by-month exposure
- Audit trail
Connects to P6 · Asta · OPC · Safran
Who is this for?
Planners and schedulers
The calendar logic for the tender programme, activity by activity, defensible when the client asks.
Estimators
The lost-day count behind prelims and weather risk pricing, at the confidence level the bid strategy needs.
Quantity surveyors and commercial managers
The baseline that later programme re-runs (4.1) and any claim (5.1 and 5.2, coming soon) will be compared with.
Risk managers
The P-values that feed the QSRA (3.2) and the weather exposure the project retains.
More for: Planners and schedulers · Estimators
Standards and contracts referenced
- NEC4 clause 60.1(13) (allowance vs compensation threshold)
- JCT Relevant Event: exceptionally adverse weather
- SCL Delay and Disruption Protocol
- APM Planning, Scheduling, Monitoring and Control guide
- Client-specific requirements, where the client or framework sets them.
400+ projects. £50bn+ of infrastructure. Morgan Sindall attributed 34% of time risk to weather across 15 projects and had clients accept it for the first time.
Priced from 1,500 credits. Results in as little as 4 minutes.
Sign up free with 1,000 credits and no card. The exact price shows in the app before you confirm.
Running it across a division? See credit packs →
Questions about weather downtime allowance
Can't find it? Email sales@ehab.co.
How much weather should a UK tender programme allow?
What is the difference between P50 and P80 downtime?
Which activities are weather-sensitive and what thresholds apply?
Can the calendars be imported into Primavera P6 and Asta Powerproject?
How does the allowance relate to the NEC contract weather line?
Was this the method adopted on the SMP Alliance?
What if my programme has no activity codes?
Often run with the Weather Downtime Allowance Report
3.2QSRA Weather Risk Model
✓ ReviewedPut realistic weather risk into your QSRA
Starting from 2,250 credits per programme
What it doesReplaces a single generic weather assumption with linked weather risk distributions for the activities actually exposed.
You getWeather risk distributions · Correlation structure · P50/P80 dates · Tornado contribution
Connects to Safran · Acumen · PRA · OPC · N&L
4.1Live Weather Calendar Service
⚡ InstantIs your programme still on the tender weather calendars?
Starting from 100 credits per site per month
What it doesRe-runs the weather risk on each programme update you import and generates fresh weather calendars to import into P6 or Asta, or syncs them into OPC, on demand.
You getRefreshed weather calendars · Revised P50/P80 completion · Calendars for P6, Asta and OPC
Connects to P6 · Asta · OPC
3.3NEC Contract Weather Baseline
⚡ InstantSet the NEC weather baseline for the site
Starting from 350 credits per contract
What it doesCalculates the monthly 1-in-10-year weather values for the NEC Contract Data from the site's own 45-year record.
You getContract Data schedule · Monthly 1-in-10-year values · Bespoke measurement options
Output PDF report
Written by WeatherWise team, EHAB. Method reviewed September 2026. How WeatherWise calculates site weather.