NEC Contract Weather Baseline3.3⚡ Instant

Set the weather line for your site.

NEC 1-in-10 values from your site's record — not a station 30 km away.

Under NEC4, weather becomes a compensation event when a measured value at the place stated in the Contract Data is shown by the contract's weather data to occur on average less than once in ten years. WeatherWise sets that 1-in-10-year line for every month and each standard measurement from the site's own 45-year record, so both parties can set the site's figures beside the named weather station's before they sign.

Starting from 350 credits per contract

Your first run is covered by your 1,000 free credits.

CONTRACT WEATHER LINE · NEC 3.3 RAIN>5MMFROSTSNOWJFMAMJJASOND31 km · +84 mSTN
as little as 2 min · 4 stepsContract Data schedule

Today vs WeatherWise: time and money

ComparedBy hand, todayWith WeatherWise
What it involvesThe contract weather line is set today from a Met Office report costing about £250, based on a 1971–2010 analysis. The station that report describes can be tens of kilometres from the site.Calculates the monthly 1-in-10-year weather values for the NEC Contract Data from the site's own 45-year record.
Time and cost~£250 Met Office report on a 1971–2010 analysis · station tens of km awayAs little as 2 min · 4 steps · ⚡ Instant · up to 720× fasterFirst run covered by your 1,000 free credits. The exact price shows in the app before you confirm.

By-hand figures are EHAB market benchmarks. Where they come from.

Video: Downtime Summary Report, explained

Downtime Summary Report, explained · 3m4sWatch on YouTube →

NEC contract weather baseline: how it's done today

NEC4 clause 60.1(13) says weather is a compensation event when it exceeds the one-in-ten-year value. That value comes from a report built on a 1971–2010 analysis, for a nominated station that may be nowhere near the site. Both parties price a risk neither has measured. Everything below the threshold sits with the contractor.

Today, the NEC contract weather line is usually set from a standard station report, in four steps.

  1. Buy the standard historical weather report for the nominated station.
  2. Nominate that weather station in the Contract Data.
  3. Hope the weather station is representative of the site.
  4. Find out it is not when the first weather compensation event is argued.

What WeatherWise does instead

Enter the site. We produce the one-in-ten value for every calendar month, for every default measurement — cumulative rainfall, days over 5 mm, air frost, snow lying — from 45 years of record at the site's grid cell. Add wind, ground temperature or wave height if those are what actually stop your work; the clause allows it, almost nobody does it. Then set them beside the nominated station's figures before you sign.

Why the Met Office 1-in-10 line can be wrong for your site · 2m55sWatch on YouTube →

How is it calculated?

WeatherWise uses 45 years of world-leading reanalysis datasets, up to 9 km grid, for the site, running to last year rather than stopping in 2010. For each calendar month and each measurement, such as cumulative rainfall, days with more than 5 mm of rain, days of air frost and days of snow lying, it estimates from that record the value that occurs on average less than once in ten years. As an Instant workflow, results pass automated checks and can return in as little as a few minutes as a Contract Data schedule. Full method: see our method page.

What you get

  • Contract Data schedule
  • Monthly 1-in-10-year values
  • Bespoke measurement options

Output  PDF report

Who is this for?

Quantity surveyors and commercial managers

Negotiate the Contract Data weather line with evidence instead of accepting the client's station.

Estimators

Understand how much weather the contractor carries before the threshold is reached.

Contract administrators and clients

A documented, reproducible baseline that reduces later dispute.

More for: Quantity surveyors and commercial managers · Estimators

Standards and contracts referenced

Proof

Baselines run to last year, not 2010.

Start free. Get your first result today.

Your first run is covered by your 1,000 free credits. Results in as little as 2 minutes. No card required.

Running it across a division? See credit packs →

Questions about NEC contract weather baseline

Can't find it? Email sales@ehab.co.

What is the 1-in-10-year weather line in an NEC contract?

The 1-in-10-year weather line is the value of each weather measurement, for each calendar month, that the contract's weather data show occurs on average less often than once in ten years. Under NEC4 clause 60.1(13), weather beyond that line at the place stated in the Contract Data is a compensation event, and only the difference above the line counts. Weather below the line stays with the contractor.

Which weather measurements are usually specified?

NEC4 Contract Data usually specifies four weather measurements for each calendar month: cumulative rainfall, the number of days with rainfall over 5 mm, the number of days with minimum air temperature below 0°C, and the number of days with snow lying at a stated time. WeatherWise produces the 1-in-10-year value for each. It can also add measurements such as wind, ground temperature or wave height, where those stop the work.

What if the named weather station is far from the site?

If the named weather station is far from the site, or at a different height, its records may not reflect the weather the site actually gets, and the 1-in-10-year line can be set too high or too low; one example had a station 31 km away and 84 m higher than the site. WeatherWise gives the 1-in-10-year values from the site's own record, so the parties can set them beside the station's figures before the contract is signed and agree the place and weather data on evidence.

Can the baseline be used for JCT or FIDIC contracts?

Yes, as evidence, although neither JCT nor FIDIC sets a 1-in-10-year test. Under JCT, exceptionally adverse weather is a Relevant Event and can entitle the contractor to more time; under FIDIC, exceptionally adverse climatic conditions are a ground for extension under sub-clause 8.4(c) (1999) or 8.5(c) (2017) of the Red Book. A site-specific WeatherWise baseline helps show what is normal for each month. Whether weather was exceptional is for the contract administrator or tribunal to decide.

How will this connect to the monthly compensation event check (5.1, coming soon)?

The contract weather baseline sets the 1-in-10-year line, and the monthly compensation event check (5.1, coming soon) will measure each month against it. On the first of each month, WeatherWise will compare the recorded measurements with the baseline, isolate the excess over the line, count down the eight-week notification period under NEC4 clause 61.3 and draft the notice. The evidence will support a compensation event; whether it is accepted is for the Project Manager or a tribunal.

Often run with the NEC Contract Weather Baseline

Coming soon
WEATHER CLAIM · MONTHLY CHECK 5.1 JFMAMJJASOND1-IN-105 WKTIME BAR

5.1NEC4 Compensation Event Report

⚡ Instant

Check NEC4 weather compensation events before the time bar

Expected: Starting from 450 credits per event

as little as 3 min · 4 steps

What it will doCompares each month's recorded weather with the 1-in-10 baseline, isolates the compensable excess, counts down the time bar and drafts the notification.

You'll getMonthly exceedance check · Excess-over-baseline calculation · Time-bar countdown · Draft notice · Impacted programme

Output  Word reportConnects to  P6 · Asta

Coming soon
EVIDENCE LEDGER · WHAT IT STOPPED 4.7 12 NOV13 NOVLOST 4h14 NOV15 NOVLOST 2h16 NOVWHAT DID ITSTOP TODAY?PourLiftEarthworks

4.7Weather Evidence Ledger

⚡ Instant

Record exactly what the weather stopped each day

Expected: Starting from 100 credits per site per month

Runs daily · 5 steps

What it will doRecords weather at the site and the contract station, asks the site team to log the activities, crews and plant affected, links the record to the programme, and raises early-warning prompts.

You'll getDaily record · What-it-stopped log · Station comparison · Early-warning prompts · Claim-ready pack

Connects to  P6 · Asta

YOUR PROGRAMME × 45 YEARS OF WEATHER 3.1 P20P50P8023 DAYS

3.1Weather Downtime Allowance Report

⚡ Instant

How much weather should you allow in the bid?

Starting from 1,500 credits per programme

as little as 4 min · 5 steps

What it doesImports your programme, identifies weather-sensitive activities, applies trade-specific thresholds, runs 45 years of weather through Monte Carlo, and generates the resulting calendars for you to import into P6 or Asta, or syncs them into OPC.

You getDowntime calendars by activity type · P20/P50/P80 lost days · Month-by-month exposure · Audit trail

Connects to  P6 · Asta · OPC · Safran

Written by WeatherWise team, EHAB. Method reviewed September 2026. How WeatherWise calculates site weather.